How much rock will it take?Use the formula below to calculate your rock needs.Length X Width X Depth in decimal inches divided by 27 = Cubic YardsMultiply cubic yards by 1.3 to get tons
For example, to calculate the amount of rock required for the parking lot above:(200 X 100 X .67) divided by 27 = 496 Cubic yards496 X 1.3 = 644.8 Tons
Decimal Equivalents1" = .082" = .1673" = .254" = .335" = .426" = .507" = .588" = .679" = .7510" = .8311" = .9212" = 1.00